Progress report on “Blue II”
As of January 30, 2009

1/5/2009
We are back from the Christmas and New Year
holidays and starting work in earnest. Today
we have completed the trimming and fitting of
the dorsal fin and stabilizer fairings.
We
put a COM and ELT antenna in the dorsal fin. We
are not sure both will work due to the close
proximity of the two but hopefully we won’t be
using both at the same time.
1/16/2009 The electronics bay is filling up
nicely. The MVP-50 wiring is complete except for
one obvious error with the EI MAP sensor. We
will start on the EFIS system Monday.
We
coated the wheel wells with three coats of the
Flame Control heat barrier. The coating is not
as smooth and shiny as a quality paint job would
be, but the protection of the heat
barrier is something I believe in. An
additional benefit is that this coating is
impervious to fuel; oil, hydraulic fluid, and
chemical wash down sprays.
The
harness for the M600 ECUs is complete aft of the
firewall and mostly complete forward of the
firewall. Final wire lengths and the pinning of
the connectors is all that is needed to complete
the ECU harness on the engine.
The electrical power supply is wired to the
distribution panel. Only about 32 circuit
breakers need to be connected and laced up
before the wing goes back on.
Here it is deep into February and I am just now
getting out the January report. I must
apologize for the delay. February is a short
month but hopefully we will have the instrument
panel installed, the circuit board controlling
the landing gear, prop governor and fuel valve
to show you and a new deal with Hartzell to
advertise in our next report.
Happy Valentines Day from all of us on the Blue
Crew.
Blue
Thunder Air Racing